Construction Updates

Here you can follow the latest updates from all our construction sites. All owners also receive weekly updates in the inbox, as well as access to our 24/7 CCTV cameras.
AS OF OCTOBER 18, 2018
PATTAYA, THAILAND
ATRIUM
  • PERCENT COMPLETED 100%
OVERALL CONSTRUCTION WORK

Architecture work 100% completed.
Sanitation systems work 100% completed.
Electric system work 100% completed.

castle 1
  • PERCENT COMPLETED 100%
OVERALL CONSTRUCTION WORK

Outdoor painting work 60% completed.
Install skirting board outside 70% completed.
Tilling in room till 4th-8th floor 95% completed.
Tilling on rooftop 50% completed.
Interior plastering on 3rd-8th floor 95% completed.
Ceiling work till on 2nd-4th floor 90% completed.
Ceiling paint work till 2nd floor 70% completed.

castle 2
  • PERCENT COMPLETED 71%
OVERALL CONSTRUCTION WORK

Install precast wall on 1st-4th 95% completed.
Install precast wall on 6th floor 40% completed.
Bricklaying on 2nd and 3rd floor 85% completed.
Bricklaying on 4th floor 60% completed.
Electric system work on 2nd floor 80% completed.
Electric system work on 4th and 5th floor 20% completed.

trend 7
  • PERCENT COMPLETED 95%
OVERALL CONSTRUCTION WORK

Tiling work 100% completed.
Tilling in room till 100% completed.
Sanitation systems work 100% completed.
Electric system work 100% completed.
Sanitation systems work 95% completed.

club 3
  • PERCENT COMPLETED 84%
OVERALL CONSTRUCTION WORK

Plaster work inside on 7th floor 100% completed .
Plaster work outside 95% completed.
Tiling bathroom work on 6th-7th floor 100% completed.
Tiled for the roof work 100% completed.
Outdoor paint work 80% completed.
Interior paint work on 2nd-6th floor 80% complete.
Ceiling work on 6th floor 80% completed.
Electric system on 6th and 7th floor 100 completed.
Water drain systems work on 6th and 7th floor 100% completed.

club 4
  • PERCENT COMPLETED 15%
OVERALL CONSTRUCTION WORK

Sheeting support 3rd floor work 100% complete.
Second floor work 100% completed.

Boutique
  • PERCENT COMPLETED 18%
OVERALL CONSTRUCTION WORK

Making the clay retaining wall 55% completed.
Making the water pond for underground floor 100% completed.
Underground floor work 95% completed.

Koh samui, THAILAND
Lamai Hotel & Resort
Building A
  • PERCENT COMPLETED 56%
OVERALL CONSTRUCTION WORK

Pouring concrete main stair 3rd and 4th floor was completed.
Making steel frame fire exit stair 2nd and 3rd floor was completed.
Pouring concrete elevator wall 3rd floor was completed.
Making the wall 2nd floor.
Setting sewage pipe 1st floor 70% completed.
Setting electric pipe 2nd floor.

Lamai Hotel & Resort
Building B
  • PERCENT COMPLETED 56%
OVERALL CONSTRUCTION WORK

Pouring concrete for elevator wall 4th floor was completed.
Pouring concrete pole 4th floor was completed.
Pouring concrete main stair 2nd and 3rd floor was completed.
Setting sewage pipe 1st floor 80% completed.
Setting mail water pipe 1st floor was completed.
Making steel frame root top.

Lamai Hotel & Resort
Building C (Hotel)
  • PERCENT COMPLETED 56%
OVERALL CONSTRUCTION WORK

Pouring concrete fire exit stair 2nd and 3rd floor was complete.
Making steel frame elevator wall 4th floor.
Set up scaffolding for roof top.
Making the wall 2nd floor.

Lamai Hotel & Resort
Building D
  • PERCENT COMPLETED 56%
OVERALL CONSTRUCTION WORK

Making steel frame roof top.
Pouring concrete fire exit stair on 2nd and 3rd floor was completed.
Setting up water pipe on 1st floor was completed.
Making the wall 1st floor 80% completed.
Making the wall 2nd floor.

New Nordic Koh
Samui Water World
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK

Clear out the land

chumphon, THAILAND
Coral Beach Condominium 1
  • PERCENT COMPLETED 100%
OVERALL CONSTRUCTION WORK

Setting up the curtain 60% completed.
Waiting more electric current for run and test all the system.

Coral Beach Condominium 3
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK

Foundation work for water tank under the ground.
Pour concrete for ground floor.
Set up the sanitary system of the building.
Start to build a pole for ground floor.

VILLA PLOT 29
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK

Cutting head pile.

Villa plot 31
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK

Demarcate the land for make zoning before cut head pile.

Villa plot 36
  • PERCENT COMPLETED 100%
OVERALL CONSTRUCTION WORK

Assembling the furniture (All done).
Setting up the curtain (All done).

Villa plot 42
  • PERCENT COMPLETED 100%
OVERALL CONSTRUCTION WORK

Assembling the furniture (All done).
Setting up the curtain (done).

Villa plot 44
  • PERCENT COMPLETED 100%
OVERALL CONSTRUCTION WORK

Assembling the furniture (All done).
Setting up the curtain (done).

Phuket, Thailand
Water World
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK

Filling the roadways preparing for machine come to build retaining wall and for transport construction materials keep going.
Waiting for permission to drilling groundwater.
The piling contractor team came to explorer area before will move in the machine.

Bali, indonesia
Bali Water World
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK
For this 37th week construction report of 2018, we would like to report,

Structural works – On Progress :
Building D
– Stairs – rebar and formwork : 40%
Building E – Second floor slab works
– Rebar and formwork : 90%
– Concrete casting : 60%
Basement at C section
– Floor slab – rebar works : 90%
– Floor slab – concrete casting : 70%
– Retaining wall – rebar works : 30%
Basement at B section
– Cutting level : 40%

cambodia
Sunshine Hotel & Resort
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK

This week we’ve finished the formwork and rebar for the first floor beams and started on the formwork for the first floor slab. Next week the site will be closed for the Pchum Ben holiday.