Construction Updates

Here you can follow the latest updates from all our construction sites. All owners also receive weekly updates in the inbox, as well as access to our 24/7 CCTV cameras.

AS OF JANUARY 17, 2019

PATTAYA, THAILAND
castle 1
  • PERCENT COMPLETED 100%

OVERALL CONSTRUCTION WORK

• Outdoor painting work 95% completed.
• Install skirting board outside 90% completed.
• Dome on roof top work 95% completed.
• UPV windows work 80% completed.
• Roof work 75% completed.
• Installing the doors on 1st-8th floor 65% completed.
• Interior plastering on 2nd-8th floor 98% completed.
• Ceiling work till on 7th-8th floor 65% completed.
• Ceiling paint work till 2nd-7th floor 95% completed.
• Sanitary system pipe work 89% completed.
• Installing wash basin on 1st-8th floor 35% completed.
• Installing hot and cool fan coil unit work on 8th floor 30% completed.

castle 2
  • PERCENT COMPLETED 78%

OVERALL CONSTRUCTION WORK

• Install precast wall on 1st-8th floor 95% completed.
• Install precast wall outside on 6th-7th floor 99% completed.
• Install precast wall on the roof top 70% completed.
• Masonry work floor on 1st-6th.
• Bricklaying on 6th floor 35% completed.
• Interior plastering on 1st-5th floor 85% completed.
• Electric system work on 1st-7th floor 30% completed.

trend 7
  • PERCENT COMPLETED 100%

OVERALL CONSTRUCTION WORK

• Roofing work 100% completed.
• Plastering outside work 100% completed.
• Electric system work 100% completed.
• Sanitation systems work 95% completed.
• Installing water drain on 6th floor 100% completed.

club 3
  • PERCENT COMPLETED 92%

OVERALL CONSTRUCTION WORK

• Plaster work outside 95% completed.
• Outdoor paint work 95% completed.
• Interior paint work on 2nd-6th floor 90% complete.
• Ceiling work on 6th-7th floor 95% completed.
• Air condition work on 2nd-7th floor 90% completed.
• Electric system work on 2nd-7th floor 30% completed.
• Sanitation systems work on 2nd-7th floor 90% completed.
• Installing water drains system.

club 4
  • PERCENT COMPLETED 40%

OVERALL CONSTRUCTION WORK

• Sheeting support 7th floor work 60% complete.
• Pouring concrete on 6th floor 100% completed.
• Bricklaying on 3rd-4th floor 35% completed.
• Plaster work on 2nd floor 90% completed.
• Provisioning pillar on 7th floor 60% completed.

Boutique
  • PERCENT COMPLETED 25%

OVERALL CONSTRUCTION WORK

• Sheeting support 4th floor work 10% complete.
• Provisioning pillar on 4th floor 10% completed.

PALACE

  • PERCENT COMPLETED 0%

OVERALL CONSTRUCTION WORK

• Cutting pile of retaining wall.

Koh samui, THAILAND
Lamai Hotel & Resort
Building A
  • PERCENT COMPLETED 68%

OVERALL CONSTRUCTION WORK

• Pouring concrete fire exit stair 1st ,2nd ,3rd and 4 floor was completed.
• Plaster the wall 3rd floor was 40%
• Make the wall 3rd floor 30%
• Setting main water pipe 1st 2nd and 3rd floor.
• Setting electric pipe 3rd floor.
• Setting main water pipe 2nd and 3rd floor

Lamai Hotel & Resort
Building B
  • PERCENT COMPLETED 68%

OVERALL CONSTRUCTION WORK

• Pouring concrete main stair 1st ,2nd ,3rd and 4th floor was completed.
• Pouring concrete fire exit stair 1,2,3 and 4th floor was completed.
• Pouring concrete elevator loop top was completed.
• Making the wall 3rd floor 40%
• Setting electric pipe 4th floor.
• Setting main water pipe 3rd and 4th floor.

Lamai Hotel & Resort
Building C (Hotel)
  • PERCENT COMPLETED 68%

OVERALL CONSTRUCTION WORK

• Pouring concrete main stair 1st ,2nd ,3rd and 4th floor was completed.
• Pouring concrete fire exit stair 1,2,3 and 4th floor was completed.
• Pouring concrete elevator loop top was completed.
• Setting main water pipe 1st 2nd and 3rd floor.
• Setting electric pipe 1st 2nd and 3rd floor.
• Making the wall 1st and 2nd floor was completed.

Lamai Hotel & Resort
Building D
  • PERCENT COMPLETED 68%

OVERALL CONSTRUCTION WORK

• Pouring concrete main stair 1st,2nd,3rd and 4th floor was completed.
• Pouring concrete fire exit stair on 1st,2nd,3rd and 4th floor was completed.
• Pouring concrete elevator loop top was completed.
• Plaster the wall 1st floor was completed.
• Making the wall 3rd floor.
• Setting electric 3rd floor.
• Setting up main water pipe on 2nd and 3rd floor.

New Nordic Koh
Samui Water World
  • PERCENT COMPLETED 0%

OVERALL CONSTRUCTION WORK

• Clear out the land

chumphon, THAILAND
Coral Beach Condominium 3
  • PERCENT COMPLETED 28%

OVERALL CONSTRUCTION WORK

• Put plank slap for rooftop (done).
• Pouring the concrete for rooftop.
• Bricklaying on 1st floor.

VILLA PLOT 29
  • PERCENT COMPLETED 28%

OVERALL CONSTRUCTION WORK

• Working on roof structure.
• Start roofing tile.
• Bricklaying in the villa.

Villa plot 31
  • PERCENT COMPLETED 26%

OVERALL CONSTRUCTION WORK

• Working on roof structure.
• Bricklaying in the villa.

Phuket, Thailand
Water World
  • PERCENT COMPLETED 0%

OVERALL CONSTRUCTION WORK

• To wiring temporary electric cables have been done in these week.

Bali, indonesia
Bali Water World

OVERALL CONSTRUCTION WORK

For this 54th week construction report of 2018, we would like to report,

1. Structural works :
a. Building E – First floor
– Column – rebar and formwork : 60%
b. Building B – First floor
– Slab – rebar, formwork & concrete casting : 100%
– Column – rebar, formwork & concrete casting : 40%
c. Building C – First Floor
– Column – rebar, formwork & concrete casting : 30%

2. MEP works
a. Building D – plumbing works : 90%
b. Building E – First floor – plumbing works : 80%

3. Architectural works
a. Building E – First Floor – wall works : 80%
b. Building E – Second Floor – wall works : 40%
c. Building E – Third Floor – wall works : 20%

cambodia
Sunshine Hotel & Resort

OVERALL CONSTRUCTION WORK

A lot happening on site now as the building is getting higher and the ground is starting to dry up after the rainy season. This week we cast the concrete for the sixth floor slab, continued with the masonry work, started on the retaining wall, continued with the plumbing, prepared to cast the concrete for the base for the wastewater treatment tank and continued with the stairs.