Construction Updates

Here you can follow the latest updates from all our construction sites. All owners also receive weekly updates in the inbox, as well as access to our 24/7 CCTV cameras.
AS OF JULY 17, 2018
PATTAYA, THAILAND
ATRIUM
  • PERCENT COMPLETED 100%
OVERALL CONSTRUCTION WORK

Furniture work on 6th floor.
Install equipment in room till 8th floor.
Install electric and water pump till 7th floor.
Interior paint work 87%.
 Finished outdoor paint work.
 Testing water system till 7th floor.

castle 1
  • PERCENT COMPLETED 99%
OVERALL CONSTRUCTION WORK

Tiling bathroom walls till 5th floor 60% completed .
Install the tiles in room till 5th floor 60% completed.
Install skirting board outside 15% completed.
Interior plastering till 6th floor 85% completed..
Ceiling paint work till 2nd floor 70% completed.
Install the water drainage till 8th floor 15% completed.
Electric work till 7th floor.

castle 2
  • PERCENT COMPLETED 59%
OVERALL CONSTRUCTION WORK

Install the precast wall till 2nd floor 80% completed.
Bricklaying on 1st floor 40% completed.

trend 7
  • PERCENT COMPLETED 81%
OVERALL CONSTRUCTION WORK

Ceiling work on 6th floor 85% completed.
Finished laying tiles on 7th floor.
Electric wiring work on 7th floor.
Interior paint work.

club 3
  • PERCENT COMPLETED 72%
OVERALL CONSTRUCTION WORK

Install electric wiring on 7th floor.
Finished Interior plaster till 6th floor.
Install the ceiling till 3rd floor 90% completed.
Finished electric wiring work on 6th floor.
Finished water drainage on 7th floor.

club 4
  • PERCENT COMPLETED 4%
OVERALL CONSTRUCTION WORK

Take out the soil and head piles cutting 70% completed.
Open footing 70% completed.
Cutting the needle base 70% completed.
Start basement 30% completed.

Boutique
  • PERCENT COMPLETED 7%
OVERALL CONSTRUCTION WORK

Finished pouring concrete for footings 56% completed.
Making the clay retaining wall 41% completed.

Koh samui, THAILAND
Lamai Hotel & Resort
Building A
  • PERCENT COMPLETED 43%
OVERALL CONSTRUCTION WORK

Make steel frame 3rd floor 30% completed.
Setting up pipe to put electric cable on 1st floor.
Setting up steel frame stair 2nd and 3rd floor.
Making wall on 1st floor.

Lamai Hotel & Resort
Building B
  • PERCENT COMPLETED 43%
OVERALL CONSTRUCTION WORK

Making stair frame on 1st floor and 2nd floor.
Making fire exit frame on 1st and 2nd floor completed.
Setting up water pipe on 1st floor.

Lamai Hotel & Resort
Building C (Hotel)
  • PERCENT COMPLETED 43%
OVERALL CONSTRUCTION WORK

Pouring concrete pole on 2nd floor was completed.
Pouring concrete stair and fire exit on 2nd floor completed.
Setting up scaffolding for 3rd floor.
Making fire exist frame for 3rd floor.

Lamai Hotel & Resort
Building D
  • PERCENT COMPLETED 43%
OVERALL CONSTRUCTION WORK

Pouring concrete pole on 2nd floor completed.
Making steel wall tie elevator 2nd floor 70% completed.
Making fire exit frame on 1st and 2nd floor.

New Nordic Koh
Samui Water World
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK

Clear out the land

chumphon, THAILAND
Coral Beach Condominium 1
  • PERCENT COMPLETED 99%
OVERALL CONSTRUCTION WORK

Testing electric system.
Cleaning inside and around the building.
Check work for the exterior and interior paint.
Install the elevator in the building (almost finish)

Coral Beach Condominium 3
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK

Start pilling for the base work of building.

Villa plot 36
  • PERCENT COMPLETED 99%
OVERALL CONSTRUCTION WORK

Repainting interior and exterior.
Testing air-con system.
Testing electric system.
Cleaning inside and around the vila.
Assembling the furniture.
Start to build the gate.

Villa plot 42
  • PERCENT COMPLETED 99%
OVERALL CONSTRUCTION WORK

Repainting interior and exterior.
Testing air-con system.
Testing electric system.
Cleaning inside and around the building.
Preparing the area around swimming pool before do exposed aggregate finish.

Villa plot 44
  • PERCENT COMPLETED 99%
OVERALL CONSTRUCTION WORK

Repainting interior and exterior.
Testing air-con system.
Testing electric system.
Cleaning inside and around the villa.
Assembling the furniture.

Bali, indonesia
Bali Water World
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK

The bore pile concrete casting
Piling works for retaining the wall
Pilling foundation at building D (building gym and spa)
Some construction’s materials coming
Some others construction preparation

cambodia
Sunshine Hotel & Resort
  • PERCENT COMPLETED 0%
OVERALL CONSTRUCTION WORK

Piling for building 100%
Piling for retaining wall 100%
Soil excavation of footings 65%
Cutting head of pile in building area 67%
Casting pile cap in building area 50%