Construction Updates

Here you can follow the latest updates from all our construction sites. All owners also receive weekly updates in the inbox, as well as access to our 24/7 CCTV cameras.

AS OF MARCH 13, 2019

PATTAYA, THAILAND
castle 1
  • PERCENT COMPLETED 100%

OVERALL CONSTRUCTION WORK

  • Outdoor painting work 98% completed.
  • Install skirting board outside 99% completed.
  • Tilling work on 3rd-8th floor 100% completed.
  • Tilling roof work 100% completed.
  • Dome on the roof top 95% completed.
  • Ceiling work till on 1st-8th floor 100% completed.
  • Ceiling paint work till 2nd-8th floor 97% completed.
  • Sanitary system pipe work 95% completed.
  • Installing wash basin on 1st-8th floor 50% completed.
  • Installing hot and cool fan coil unit work on 5th-6th floor 95% completed.
  • Installing builtin furniture in room.
castle 2
  • PERCENT COMPLETED 81%

OVERALL CONSTRUCTION WORK

  • Install precast wall on 1st-5th floor 95% completed.
  • Install precast wall on 6th-8th floor 99% completed.
  • Install precast wall on the roof top 99% completed.
  • Bricklaying work on 1st-4th floor 97% completed.
  • Bricklaying work on underground to roof top 70% completed.
  • Plastering work on 1st-5th floor 95% completed.
  • Tilling work on 1st-8th floor 80% completed.
  • Electric system work on 1st-3rd floor 90% completed.
  • Electric system work on 4th floor 85% completed.
  • Electric system work on 5th floor 75% completed.
  • Electric system work on 6th-7th floor 35% completed.
trend 7
  • PERCENT COMPLETED 100%

OVERALL CONSTRUCTION WORK

Installing the furniture and decorate.

club 3
  • PERCENT COMPLETED 93%

OVERALL CONSTRUCTION WORK

  • Plastering work outside 100% completed.
  • Interior paint work on 2nd-7th floor 100% complete.
  • Ceiling work on 2nd-7th floor 100% completed.
  • Testing electric water and sanitation systems.
     
club 4
  • PERCENT COMPLETED 48%

OVERALL CONSTRUCTION WORK

  • Roof structure work 80% completed.
  • Bricklaying wall on 2nd-4th floor 98% completed.
  • Bricklaying wall on 6th floor 40% completed.
  • Plastering work on 5th floor 50% completed.
  • Tilling Bathroom wall on 4th floor 30% completed.
  • Tilling in room on 3rd floor 60% completed.
  • Ceiling work on 2nd floor 40% completed.
  • Setting electric pipe on 4th floor 20% completed.
Boutique
  • PERCENT COMPLETED 32%

OVERALL CONSTRUCTION WORK

  • Pole sheeting support work on 5th floor 100% complete.
  • Floor work on 5th floor 30% completed.
  • Bricklaying work on 2nd floor 98% completed.
  • Bricklaying work on 3rd floor 20% completed.
  • Electric system work on 2nd floor 80% completed.
  • Water drains work on 3rd floor 20% completed.
PALACE
  • PERCENT COMPLETED 0%

OVERALL CONSTRUCTION WORK

  • Retaining wall beam work 100% completed.
  • Retaining wall work 100% completed.
  • Wall posts work 20% completed.
  • Pilling work 91 of 210 piles.

 

Koh samui, THAILAND
Lamai Hotel & Resort
Building A
  • PERCENT COMPLETED 76%

OVERALL CONSTRUCTION WORK

  • Set up roof tile was completed.
  • Painting skim coat wall 1st floor.
  • Plaster the wall 1st and 2nd floor was completed.
  • Bricklaying was completed.
  • Setting electric pipe 3rd floor.
  • Setting electricity on 1st floor was completed.
  • Tile laying bathroom wall 1st floor.
  • Tile laying bedroom 1st floor.
  • Setting ceiling on 1st floor.
  • Setting air condition refrigerant pipe 1st 2nd and 3rd floor was completed. 
Lamai Hotel & Resort
Building B
  • PERCENT COMPLETED 76%

OVERALL CONSTRUCTION WORK

  • Bricklaying 3rd floor was completed.
  • Bricklaying 4th floor.
  • Painting skim coat wall 1st floor.
  • Painting skim coat 2nd floor 65%
  • Setting electricity on 1st floor was completed
  • Setting electric pipe 4th floor.
  • Plaster the wall 1st and 2nd floor.
  • Tile lying bathroom wall 1st and 2nd floor.
  • Setting ceiling frame on 1st floor was completed.
  • Setting air condition refrigerant pipe 1st 2nd and 3rd floor was completed. 
Lamai Hotel & Resort
Building C (Hotel)
  • PERCENT COMPLETED 76%

OVERALL CONSTRUCTION WORK

  • Setting main water pipe 4th floor.
  • Set up roof tile was completed.
  • Setting electric pipe 1st 2nd and 3rd floor.
  • Bricklaying 4th floor 95%.
  • Setting roof tile was completed.
  • Setting electricity on 1st floor was completed.
  • Setting electricity on 2nd floor 70%
  • Plaster the wall 1st floor.
  • Setting air condition refrigerant pipe 1st 2nd and 3rd floor was completed.
  • Setting ceiling frame on 1st floor was completed.
Lamai Hotel & Resort
Building D
  • PERCENT COMPLETED 76%

OVERALL CONSTRUCTION WORK

  • Steel frame roof was completed.
  • Painting eaves 50%
  • Plaster the wall 1st floor was completed.
  • Plaster the wall 2nd 80%
  • Bricklaying 3rd floor was completed.
  • Bricklaying 4th floor.
  • Setting electric pipe 3rd floor.
  • Setting up main water pipe on 2nd, 3rd and 4th floor.
  • Main water pipe set up 1st floor was completed.
  • Setting electricity on 1st and 2nd floor was completed.
  • Setting air condition refrigerant pipe 1st 2nd and 3rd floor was completed.
  • Setting ceiling frame on 1st floor was completed.
New Nordic Koh
Samui Water World
  • PERCENT COMPLETED 0%

OVERALL CONSTRUCTION WORK

  • Piling 270 of 678 piles.
chumphon, THAILAND
Coral Beach Condominium 3
  • PERCENT COMPLETED 37%

OVERALL CONSTRUCTION WORK

  • Starting with the roof structure.
  • Install PVC tube for wire in the building.
  • Brick laying 3rd floor.
VILLA PLOT 29
  • PERCENT COMPLETED 37%

OVERALL CONSTRUCTION WORK

  • Start roofing tile (100%).
  • Wall plastering (100%).
  • Plastering for the pool.
Villa plot 31
  • PERCENT COMPLETED 37%

OVERALL CONSTRUCTION WORK

  • Working on roof structure (done).
  • Bricklaying on 2nd floor.
  • Wall plastering (30%).
  • Start working for the pool structure.
Phuket, Thailand
Water World
  • PERCENT COMPLETED 0%

OVERALL CONSTRUCTION WORK

• To wiring temporary electric cables have been done in these week

Bali, indonesia
Bali Water World

OVERALL CONSTRUCTION WORK

For this 62nd week construction report of 2019, we would like to report,

1. Structural works :
    a. Building A – Second floor
         – Slab – rebar, formwork & concrete casting : 70%
    b. Building B – Third floor
         – Slab – rebar, formwork & concrete casting : 60%
    c. Building C – Second Floor
         – Slab – rebar, formwork & concrete casting : 90%
         – Column – rebar, formwork & concrete casting : 80%
    
2. MEP works
    a. Building E – Second floor – plumbing works : 80%
    b. Building E – Third floor – plumbing works : 60%
    c. Building E – Fourth floor – plumbing works : 20%

3. Architectural works
    a. Building E – Third Floor – wall works : 90%
    b. Building E – Fourth Floor – wall works : 60%
    c. Building B – First Floor – wall works : 30%

4. Labors on site
    a. Building E : 39 labors
    b. Building C : 22 labors
    c. Building D : 16 labors
    d. Building B : 33 labors
 

cambodia
Sunshine Hotel & Resort

OVERALL CONSTRUCTION WORK

This week we cast the concrete for the tenth floor columns, started with the wiring and continued with masonry work and work on the plumbing, conduits and stairs.