Construction Updates

Printed Tue Aug 20 2019 12:23:15 GMT+0000 (Greenwich Mean Time)

Sunshine Hotel
Sihanoukville, Cambodia

This week we continued with the louvers, painting, brickwork, plastering, skim coating, ceilings, plumbing and wiring and pressure tested the water system.

NaN/5

Bali Water World A
Bali, Indonesia

 1. Structural Works
          a. Fourth Floor
              - Roof perimeter wall formwork : 55%
              - Stair formwork, rebar & concrete : 55%
     2. Architectural Works
          a. First Floor
              - Wall Works : 80%
          b. Second Floor
              - Wall Works : 80%
NaN/5

Bali Water World B
Bali, Indonesia

1. Structural Works
          a. Stair formwork, rebar & concrete  : 10%
2. MEP works
          a. Fire fighting, fire alarm, plumbing, electrical works : 42%
3. Architectural Works
          a. First floor
               - Wall works : 85%
          b. Second floor
               - Wall works : 85%
          c. Third floor
               - Wall works : 85%
          c. Basement
               - Wall works : 78%
          d. Top floor
               - Wall works : 50%

NaN/4

Bali Water World C
Bali, Indonesia

1. Structural Works
         a. Fourth Floor
              - Rebar & formworks column : 100%
              - Rebar & formworks roof slab : 75%
      2. Architectural Works
          a. First Floor   : 50%

NaN/4

Bali Water World D
Bali, Indonesia

 1. Architectural Works
         First - second floor : 93%

NaN/5

Bali Water World E
Bali, Indonesia

 1. Structural works
         a. Pool (In front of building E)
             Leek test process   : 75%
     2. MEP Works
         a. Third floor - plumbing works : 96%
         b. Fourth floor - plumbing works : 96%
     3. Architectural Works
         a. First floor - floor works       : 85%
         b. Second floor - floor  works : 85%
         c. Third floor - floor works      : 85%
         d. Fourth floor - floor works    : 85%

NaN/5

Chumphon Building 3
Chumphon, Thailand

Completed: 58 %
  • Working on roof structure (100%).
  • Plastering wall 2st floor.
  • Tiling work in bathroom.
  • Wall behind building (done).
  • Aluminum fence install (done).
  • Start ceiling work.
  • Start pool structure middle of the building.
  • Install electric system.
NaN/10

Chumphon Coral Beach Villas Plot 29
Chumphon, Thailand

  • Painting work (done).
  • Adjust the land around villa (done).
  • Building fence around the villa (done).
  • Tile work (done).
  • Install door and window frame (done).
  • Install air-con in living room and bedroom (done).
  • Start system work for swimming pool.
  • Install sanitary ware.
  • Assemble furniture.
NaN/5

Chumphon Coral Beach Villas Plot 31
Chumphon, Thailand

  • Ceiling work.
  • Banister work.
  • Tile work in 2nd floor.
  • Painting work.
  • Install door and window frame.
  • Install air-con in living room and bedroom.
  • Start system work for swimming pool.
  • Install sanitary ware.
  • Tile work for the pool.
  • Assemble furniture.
NaN/7

Samui Resort building A
Koh Samui, Thailand

Completed: 99 %
  • Lamp installation 2nd floor completed.
  • Tile laying bathroom 4th floor completed
  • Tiling the corridor floor 3rd
  • Setting up ceiling 3rd floor.
  • Leveling the balcony 3rd floor, preparing tiles
  • Install fire extinguisher 1st - 4th floor completed.
  • Tiling the corridor 1st and 2nd floor.
  • Install Key-tech 1st and 2nd floor.
  • Setting ceiling 4th floor.
  • Primer painting outside building  2nd and  3rd  floor.
  • Painting ceiling 3rd floor.50%
  • Making counter frame 4th floor
  • Tile laying fire exit stair 1st floor.
  • Install the bell lights on the 3rd floor.
  • Install the power cord under the stairs 2nd floor.
NaN/11

Samui Resort building B
Koh Samui, Thailand

Completed: 99 %
  • Plastering outside the building 95%.
  • Tile lying bathroom 4th  floor completed.
  • Setting up guard rail 3rd floor completed.
  • Setting up elevator 95%.
  • Install electrical switches and electrical plugs 1st and 2nd floor.
  • Primer painting outside building 1st and 2nd floor.
  • Primer paint guard rail 2nd floor.
  • Install Key-Tech 2nd floor.
  • Tiling the corridors   2nd floor.
  • Test the fire extinguishing system.
  • Primer paint ceiling 2nd floor completed.
  • Install sanitary ware 1st to 4th floor.
  • Install ventilation fans 2nd floor.
  • Setting ceiling 4th floor 55%.
  • Tile laying 4th floor.
  • Setting aluminum 1st and 2nd floor.
  • Install smoke detector 1st and 2nd floor.
NaN/10

Samui Resort building C
Koh Samui, Thailand

Completed: 99 %
  • Painting skim coat outside building 80%.
  • Tile laying the balcony 2nd floor.
  • Install the main electrical cable set, 2nd floor.
  • Primer paint guard rail 2nd floor.
  • Setting ceiling frame 4th floor 70%.
  • Install Key-Tech 2nd floor.
  • Tiling the corridor 1st floor completed.
  • Painting skim coat outside building.
  • Setting up elevator 95%.
  • Install rainwater pipes.
  • Install the door frame1st floor.
NaN/9

Samui Resort building D
Koh Samui, Thailand

Completed: 99 %
  • Plastering outside the building completed.
  • Setting up guard rail 4th floor 40%
  • Tile laying bedroom 2nd floor 70%
  • Setting ceiling on 3rd floor 90%
  • Setting up guard rail 4th floor 40%
  • Install sanitary ware completed.
  • Setting ceiling frame 3rd floor 90%
  • Setting aluminum 1st floor and 2nd floor.
  • Setting up elevator 95%
  • Install smoke detector 1st floor.
NaN/11

Samui Water World building A
Koh Samui, Thailand

  • Cut the foundation pile completed.
  • Steel pole extraction completed.
  • Pouring concrete 1st floor.
  • Setting groundwater storage tank frame.
  • Pouring concrete underground storage tanks.
  • Install the plumbing system 1st floor.
  • Setting main pipe system ground floor.
  • Setting steel floor frame 1st floor.
  • Install waterproofing plastic sheets.
NaN/6

Samui Water World building B
Koh Samui, Thailand

  • Setting groundwater storage tank frame 1St  and 2nd
  • Steel pole tile 1st floor.
  • Tie steel frame groundwater storage tank.
  • Pouring concrete underground storage tanks 1st and 2nd
  • Pouring concrete storage water tank wall.
  • Install the plumbing system 1st floor.
NaN/6

Samui Water World building C
Koh Samui, Thailand

  •  Pouring concrete base
  • Pouring concrete the groundwater storage tank
  • Install the plumbing system 1st floor.
  • Pile extraction.
  • Setting steel floor frame 1st floor
  • Steel pole tile 1st floor.
NaN/5

Samui Water World building D
Koh Samui, Thailand

  • Cut the foundation pile
  • Steel pole tie 1st floor
  • Pouring concrete base
  • Tied steel beam pool bar
  • Setting main water pipe system 1st floor
  • Tied steel frame pool bar wall.
  • Install the plumbing system 1st floor.
NaN/4

Boutique
Pattaya, Thailand

Completed: 60 %
  • Plastering work on 4th floor 95% completed.
  • Bricklaying on 6th floor 60% completed.
  • Bricklaying on 7th floor 40% completed.
  • Tilling bathroom work on 4th floor 80%completed.
  • Ceiling work on 1st-3rd floor 75% completed.
  • Ceiling work on 4th floor 60% completed.
  • Electric system work on 2nd-3rd floor 92% completed.
  • Electric system work on 4th floor 60% completed.
  • Water drains work on 2nd-7th floor 85% completed.
NaN/11

Castle 1
Pattaya, Thailand

Completed: 100
  • Construction work 100% completed.
  • Architecture work 100% completed.
  • Sanitation systems work 100% completed.
  • Electric work 100% completed.
NaN/12

Castle 2
Pattaya, Thailand

Completed: 95 %
  • Bricklaying work on the underground floor 95% completed.
  • Plastering work on 1st-8th floor 98% completed.
  • Plastering wall work on rooftop floor 98% completed.
  • Plastering underground wall 80% completed.
  • Wash basin counter work 85% completed.
  • Tilling work on 1st-8th floor 98% completed.
  • Tilling work on rooftop floor 98% completed.
  • Tilling main stair work 99% completed.
  • Install skirting boards 80% completed.
  • Install wood door 30% completed.
  • Outdoor painting work 35% completed.
  • Wall painting 40% completed.
  • Ceiling work 65% completed.
  • Sky roof work 100% completed.
  • Elevator work 75% completed.
  • Electric system work 2nd-7th floor 98% completed.
  • Water system work 96% completed.
NaN/11

Castle Hotel
Pattaya, Thailand

  • Installing the roof top.
  • Ceiling work.
NaN/8

Club 3
Pattaya, Thailand

Completed: 100
  • Almost completed (Just wait for cleaning).
  • Open on August 2019
NaN/9

Club 4
Pattaya, Thailand

Completed: 83 %
  • Plastering on 1st floor 40% completed.
  • Tilling Bathroom wall on 2nd-7th floor 99% completed.
  • Tilling the walk way on 2nd-7th floor 99% completed.
  • Tilling in room on 2nd-7th floor 99% completed.
  • Tilling balcony on 2nd-7th floor 99% completed.
  • Tilling balcony on 2nd-4th floor 99% completed.
  • Tilling main stair on 1st-7th floor 99% completed.
  • Tilling fire stair on 1st-7th floor 99% completed.
  • Ceiling work on 2nd-7th floor 99% completed.
  • Painting outdoor work 90% completed.
  • Painting in the room on 5th-7th 80% completed.
  • Installing UPVC window work on 2nd-7th floor 98% completed.
  • Installing UPVC door work on 2nd-7th floor 98% completed.
  • Water system work 90% completed.
  • Setting electric pipe on 2nd-7th floor 99% completed.
  • Install electrical equipment on 2nd-7th 99% completed.
NaN/11

Club 5
Pattaya, Thailand

  • Open the foundation piles 52% completed.
  • Cutting foundation piles 52% completed.
  • Adjust the soil 52% completed.
  • Pouring concrete base.
NaN/6

Palace Hotel
Pattaya, Thailand

Completed: 9 %
  • Beam work 95% completed.
  • Retaining wall 40% completed.
  • Underground floor work 70% completed.
NaN/8

Trend 7
Pattaya, Thailand

Completed: 100
  •  Installing the furniture and decorate.
NaN/7

Bangtao Water World B
Phuket, Thailand

  • Merit celebration for opening offices.
  • Continue piling B and C building.
  • Roadwork from public road to project.
  • Retaining wall.
  • Extra heavy equipment arriving.
  • Construction meetings by management.
NaN/5