Sunshine Hotel
Sihanoukville, Cambodia

This week we continued with floor and wall tiles, waterproofing, wall plastering, ceiling work, installing handrails on the balconies, beam installation for elevators, brick wall installation, rebar and I-beam installation for decking.

NaN/10

Bali Water World A
Bali, Indonesia

     1. Structural Works
          - Building A : 98%
          - Lower Ground Floor & Pool  : 43%
     2. Architectural Works
          - Building A  : 36%
     3. Mechanical, Electrical and Plumbing works (MEP)
          - Building A  : 34%

NaN/6

Bali Water World B
Bali, Indonesia

1. Structural Works
          a. Building B : 98%
          b. Lower Ground Floor & Pool  : 43%
      2. Architectural Works
          a. Building B  : 40%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building B : 45%

NaN/5

Bali Water World C
Bali, Indonesia

1. Structural Works
         a. Building C : 98%
         b. Lower Ground Floor & Pool : 43%
      2. Architectural Works
          a. Building C : 41%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building C : 31%

NaN/6

Bali Water World D
Bali, Indonesia

1. Structural Works
         a. Building D : 100%
         b. Pool : 98%
     2. Architectural Works
          a. Building D : 94%
     3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building D : 75% 

NaN/5

Bali Water World E
Bali, Indonesia

   1. Structural Works
         a. Building E : 100%
         b. Pool : 98%
     2. Architectural Works 
         a. Building E : 76%
     3. Mechanical, Electrical and Plumbing works (MEP)
         a. Building E : 72%

NaN/5

Chumphon Building 3
Chumphon, Thailand

Completed: 86 %
  • Working on roof structure (100%)
  • Waiting for electric work
  • Waiting for install doors and windows
  • Tiling work in the pool
  • Cleaning around the building
  • Put the waste water pipe behind the building
NaN/10

Samui Resort building A
Koh Samui, Thailand

COMPLETED
  • Install the power cord in to the Main Distribution Board.
  • Install aisles lamp 3rd floor.
  • Install doors flame and door 4th floor.
  • Painted door jamb 4th floor was completed
  • Install guardrail main stair 2nd and 3rd floor.
  • Install guardrail fire exit stair 2nd and 3rd floor
  • Install  MDB Boxes.
  • Install air condition 4th floor 80%
  • Setting guard rail main stair 1st-4th floor.
  • Setting telephone box control 1st – 4th floor.
  • Tile the front elevator 1st-4th floor.
  • Painted inside 1st-2nd floor.
  • Fire fighting system test.
  • Prepare for gardening
  • Install sanitary ware on 3-4 floors.
  • Keep external color work.
NaN/10

Samui Resort building B
Koh Samui, Thailand

COMPLETED
  • Install the power cord in to the Main Distribution Board.
  • Install electrical cabinet for 4th floor.
  • Setting up guard rail 4th floor.
  • Install support water meter.
  • Install glass and aluminum frame 1st and 2nd floor.
  • Setting main water for tub 1st – 4th floor.
  • Tile laying tub 1st – 4th floor.
  • Install water pipes, bathtub water systems.
  • Setting telephone box control 1st – 4th floor.
  • Install granite on the sink counter 1st – 3rd floor.
  • Install aluminum door 1st -2nd floor 95%
  • Installing electrical plugs and switches 3rd floor 70%
  • Install washbasin 3rd floor.
  • Leveling the room floor, 4th floor.
  • Floor tile + balcony 4th floor.
  • Leveling the floor on the 4th floor.
  • Laying floor tiles for walkways on the 4th floor. 
NaN/10

Samui Resort building C
Koh Samui, Thailand

COMPLETED
  • Install the ceiling structure 4th floor.
  • Install up guard rail 4th floor.
  • Tile laying fire exit stair 3rd and 4th floor.
  • Install granite on the wash basin 4th floor.
  • Check the completion of the cement under main stair 1st – 4th floor
  • Painting ceiling 4th floor.
  • Install guardrail fire exit stair 2nd and 3rd floor
  • Setting guard rail fire exit stair 2nd-3rd floor.
  • Install the lamp 4th floor.
  • Setting up the electric system into the elevator.
  • Painted inside 1st-2nd  floor 95%
  • Collect paint work around the floor 1-3.
  • Keep external color work.
NaN/8

Samui Resort building D
Koh Samui, Thailand

COMPLETED
  • Install SHERA wall.
  • Install rainwater pipes.
  • Plastering elevator wall.
  • Install electrical cabinets for 3rd and 4th floor.
  • Install air conditioned 4th floor (80%).
  • Tile grout elevator wall 1st – 4th floor.
  • Setting up ceiling under main stair 1st- 3rd  floor.
  • Setting ceiling 4th floor.
  • Install water pump for the building.
  • Painting skim coat 4th floor.
  • Masonry in front of the project to prepare the project signboard.
  • Plaster wall water pump room.
  • Firefighting system test.
  • Testing air conditioning systems.
  • Install the railing on the 4th floor (90%).
  • Install granite counters on floors 2-4 (95%)
  • Paint the 4th floor ceiling (40%) 
NaN/7

Samui Water World building A
Koh Samui, Thailand

  • Install the plumbing system 1st floor.
  • Setting main pipe system 1st   floor.
  • Tied steel frame  2nd floor.
  • Steel pole tied 2nd floor.
  • Setting up floor frame 2nd floor.
  • Pouring concrete 2nd floor.
  • Steel frame elevator wall 2nd floor.
  • Steel frame main stair 1st and 2nd floor.
  • Installation of a water supply pipe system 2nd floor.
  • Steel tie and assemble with elevator wall, 2nd floor
  • Steel tie and assemble on the 2nd floor column
  • Pull the floor posts on the 2nd floor
  • Remove the floor plan, floor 2
NaN/6

Samui Water World building B
Koh Samui, Thailand

  • Setting main pipe system 1st   floor.
  • Install the plumbing system 1st floor.
  • Pouring concrete beam.
  • Setting ground water system.
  • Pouring concrete elevator wall 2nd floor.
  • Setting pole frame 2nd floor.
  • Steel floor frame 2nd floor.
  • Tie steel frame 2nd floor.
  • Tie steel frame elevator wall 2nd floor.
  • Installation of a water supply pipe system
  • Setting electric pipe 1st floor.
  • Setting up scaffolding to receive floor 3
  • Build a wall with lintels on the 1st floor 
NaN/6

Samui Water World building C
Koh Samui, Thailand

  • Tied steel frame 2nd floor.
  • Tied steel frame elevator wall 2nd floor.
  • Pouring concrete pole 2nd floor.
  • Steel frame elevator wall 2nd floor.
  • Steel frame main stair 1st-2nd floor.
  • Installation of a water supply pipe system
  • Setting scaffold for 3rd floor.
  • Steel floor frame 3rd floor.
  • Setting electric pipe 1st floor.
  • Constructed 3rd floor
  • Place the floor post on the 3rd floor
  • Piping and plumbing system level 1
  • Assembled the bathroom 1st floor.
  • Wall on the 1st floor.
NaN/6

Samui Water World building D
Koh Samui, Thailand

  • Tied steel beam pool bar.
  • Setting main water pipe system 1st floor.
  • Tied steel frame pool bar wall.
  • Install the plumbing system 1st floor.
  • Tile steel pole frame 2nd floor.
  • Setting up floor frame 2nd floor.
  • Tied steel frame  2nd floor.
  • Tie steel frame main stair 1st-2nd floor.
  • Installation of a water supply pipe system
  • Tie steel frame main stair 1st-2nd floor
  • Pouring concrete on floors 1-2
  • Pouring concrete on the 2nd floor
  • Reproduction and curing of concrete posts on the 2nd floor
  • Setting up scaffolding to receive floor 3 
NaN/6

Boutique
Pattaya, Thailand

Completed: 70 %
  • Exterior plastering work 98% completed.
  • Rooftop work 98% completed.
  • Tilling bathroom wall on 3rd-7th floor 95% completed.
  • Tilling on 1st floor 60% completed.
  • Tilling  on 2nd-6th floor 80% completed.
  • Tilling on 7th floor 70% completed.
  • Ceiling work on 1st-4th floor 75% completed.
  • Ceiling work on 5th-6th floor 70% completed.
  • Ceiling work on 7th floor 15% completed.
  • Electric system work on 2nd-4th floor 92% completed.
  • Electric system work on 5th-6th floor 60% completed.
  • Water drains work on 2nd-7th floor 85% completed.
NaN/12

Castle 2
Pattaya, Thailand

Completed: 99 %
  • Bricklaying work on the underground floor 99% completed.
  • Plastering underground wall 99% completed.
  • Plastering work on 1st-8th floor 99% completed.
  • Wash basin counter work 88% completed.
  • Plastering wall work on rooftop floor 100% completed.
  • Tilling work on 1st-8th floor 99% completed.
  • Tilling work on rooftop floor 100% completed.
  • Install skirting boards 98% completed.
  • Install wood door 45% completed.
  • Outdoor painting work 51% completed.
  • Interior wall painting work 90% completed.
  • Ceiling work 96% completed.
  • Installing UPCV window on 2nd-8th floor 90% completed.
  • Shower screen work on 2nd-8th floor 30% completed.
  • Elevator work 80% completed.
  • Electric system work 1st-8th floor 99% completed.
  • Water system work 97% completed.
NaN/10

Castle Hotel
Pattaya, Thailand

  • Electric system on 2nd floor.
  • Painting ceiling work on 2nd floor.
  • Wall work on 1st floor.
  • Roof top work.
  • Installing Air condition on 2nd floor.
NaN/5

Club 4
Pattaya, Thailand

Completed: 97 %
  • Exterior painting work 100% completed.
  • Room painting on 2nd-7th 99% completed.
  • The walk way painting on 2nd-7th floor 99% completed.
  • Ceiling work on 1st floor 95% completed.
  • Ceiling work on 2nd-7th floor 100% completed.
  • Balcony guard rail painting on 2nd-7th floor 99% completed.
  • Swimming pool electrical system work 100% completed.
  • Water drains work on 2nd-7th floor 100% completed.
  • Electric work (Wait for testing).
NaN/6

Club 5
Pattaya, Thailand

Completed: 7 %
  • 2nd floor work 100% completed.
  • Pole work.
NaN/6

Palace Hotel
Pattaya, Thailand

Completed: 15 %
  • Swimming pool structure work on 1st floor 30% completed.
  • Filling the soil around buildings 40% completed.
  • 1st floor structure 20% completed.
  • Parking Structure 20% completed.
NaN/6

Bangtao Water World B
Phuket, Thailand

  • Piling work of building D
  • Digging foundation work for building B.
  • Building the retaining wall block.
NaN/3