Sunshine Hotel
Sihanoukville, Cambodia

This week we continued with wall and floor tiles, wall paintings, check line for elevator, frame for ceiling and close and paint gypsum, bench installations, formwork for louver installation, brick wall installation, wall plastering, casting concrete for the swimming pool (rooftop).

NaN/5

Bali Water World A
Bali, Indonesia

 1. Structural Works
          a. Building B : 97%
          b. Lower Ground Floor & Pool  : 36%
      2. Architectural Works
          a. Building B  : 38%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building B : 43%

NaN/4

Bali Water World B
Bali, Indonesia

 1. Structural Works
          a. Building B : 97%
          b. Lower Ground Floor & Pool  : 33%
      2. Architectural Works
          a. Building B  : 36%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building B : 40%

NaN/4

Bali Water World C
Bali, Indonesia

  1. Structural Works
         a. Building C : 97%
         b. Lower Ground Floor & Pool : 36%
      2. Architectural Works
          a. Building C : 37%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building C : 28%

NaN/4

Bali Water World D
Bali, Indonesia

 1. Structural Works
         a. Building D : 100%
         b. Pool : 97%
     2. Architectural Works
          a. Building D : 93%
     3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building D : 73% 

NaN/3

Bali Water World E
Bali, Indonesia

1. Structural Works
         a. Building E : 100%
         b. Pool : 97%
     2. Architectural Works 
         a. Building E : 76%
     3. Mechanical, Electrical and Plumbing works (MEP)
         a. Building E : 72%

NaN/5