Construction Updates

Printed Sun Sep 15 2019 08:11:52 GMT+0000 (Greenwich Mean Time)

Sunshine Hotel
Sihanoukville, Cambodia

This week we continued with the louvers, painting, brickwork, plastering, skim coating, ceilings, plumbing and wiring.

NaN/6

Bali Water World A
Bali, Indonesia

1. Structural Works
          - Building A : 96%
          - Lower Ground Floor & Pool  : 27%
     2. Architectural Works
          - Building A  : 30%
     3. Mechanical, Electrical and Plumbing works (MEP)
          - Building A  : 30%

NaN/5

Bali Water World B
Bali, Indonesia

1. Structural Works
          a. Building B : 96%
          b. Lower Ground Floor & Pool  : 27%
      2. Architectural Works
          a. Building B  : 32%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building B : 32%

NaN/4

Bali Water World C
Bali, Indonesia

1. Structural Works
         a. Building C : 96%
         b. Lower Ground Floor & Pool : 27%
      2. Architectural Works
          a. Building C : 31%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building C : 28%

NaN/4

Bali Water World D
Bali, Indonesia

1. Structural Works
         a. Building D : 100%
         b. Pool : 95%
     2. Architectural Works
          a. Building D : 86%
     3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building D : 70% 

NaN/5

Bali Water World E
Bali, Indonesia

1. Structural Works
         a. Building E : 100%
         b. Pool : 95%
     2. Architectural Works 
         a. Building E : 65%
     3. Mechanical, Electrical and Plumbing works (MEP)
         a. Building E : 69%

NaN/3

Chumphon Building 3
Chumphon, Thailand

Completed: 63 %
  • Working on roof structure (100%).
  • Tiling work in bathroom.
  • Tiling corridor.
  • Wall behind building (done).
  • Aluminum fence install (done)
  • Ceiling work.
  • Pouring the concrete for the pool (done).
  • Outdoor painting.
  • Indoor painting.
  • Start swimming pool system.
NaN/7

Chumphon Coral Beach Villas Plot 29
Chumphon, Thailand

  • Painting work (done).
  • Gardening around the villa.
  • Start system work for swimming pool.
  • Assemble furniture.
  • Start doing wall paper.
  • Install aluminum fence.
  • Sand wash around the pool.
NaN/10

Chumphon Coral Beach Villas Plot 31
Chumphon, Thailand

  • Start system work for swimming pool.
  • Gardening around the villa.
  • Tile work for the pool.
  • Assemble furniture.
  • Start doing wall paper.
  • Install aluminum fence.
NaN/9

Samui Resort building A
Koh Samui, Thailand

Completed: 100
  • Install the water meter on the  1st to 4th floor.
  • Tile laying fire exit stair 1st and 2nd  floor.
  • Tiling main stairs 2nd and 3rd  floor.
  • Tiling the corridor 4th floor.
  • Install doors frame and door 4th floor.
  • Setting up guard rail 3rd floor.
  • Setting ceiling 4th floor 55%
  • Install the power cord in to the Main Distribution Board.
  • Install lamp wall.
  • Install sanitary ware 1st and  3rd floor.
  • Install granite on the wash basin 1st and 2nd floor.
  • Install sandstone on the wall.
  • Make a box for fire hydrants 1st -4th floor.
  • Potted plastering 4th floor.
NaN/10

Samui Resort building B
Koh Samui, Thailand

Completed: 100
  • Plastering outside the building 95%.
  • Setting up elevator 95%.
  • Install electrical switches and electrical plugs 1st and 2nd floor.
  • Tiling the corridors   2nd  and 3rd floor.
  • Tile laying main stair 1st and 2nd  floor.
  • Tile laying 3rd floor.
  • Install sanitary ware 1st to 4th floor.
  • Install ventilation fans 2nd floor.
  • Setting up guard rail 4th  floor.
  • Setting ceiling 4th floor.
  • Install the power cord in to the Main Distribution Board.
  • Install doors 1st floor.
  • Install floor tiles  2nd  floor.
  • Install sandstone on the wall.
  • Install main water meter 1st- 4th  floor.
NaN/11

Samui Resort building C
Koh Samui, Thailand

Completed: 100
  • Install air conditioner  2nd floor.
  • Install the power cord in to the Main Distribution Board.
  • Plastering outside the building.
  • Tiling the corridors   2nd and  3rd floor.
  • Tile laying main stairs 2nd and 3rd  floor.
  • Install the ceiling structure 4th floor.
  • Install lamp wall.
  • Fire testing system.
  • Install the main electrical cable set, 2nd floor
  • Painting guard rail 1st floor.
  • Setting up elevator 95%.
  • Install the door frame completed.
  • Tile laying fire exit stair 2nd and 3rd floor.
  • Install sandstone on the wall.
NaN/10

Samui Resort building D
Koh Samui, Thailand

Completed: 100
  • Tiling main stairs 1st and 2nd floor.
  • Install air conditioner  2nd floor.
  • Tile laying fire exit stair 1st and 2nd  floor was completed.
  • Tile laying fire exit stair 3rd and 4th floor.
  • Tiling the corridors   2nd and 3rd floor.
  • Install floor tiles 2nd floor.
  • Plastering elevator wall.
  • Setting up guard rail 4th floor 60%
  • Install electrical cabinets in the room 3rd floor.
  • Painting ceiling 3rd floor.
  • Install air conditioned 4th floor.
  • Install main water meter 1st and 2nd floor.
  • Setting up elevator 95%.
NaN/8

Samui Water World building A
Koh Samui, Thailand

  • Pouring the base concrete.
  • Pouring concrete post tensioned.
  • Pouring concrete 1st floor
  • Setting groundwater storage tank frame.
  • Pouring concrete underground storage tanks 1-2.
  • Install the plumbing system 1st floor.
  • Setting main pipe system 1st   floor.
  • Pouring concrete elevator wall 1st floor.
  • Tied beam frame.
  • Pouring concrete pole 1st floor.
NaN/6

Samui Water World building B
Koh Samui, Thailand

  • Setting groundwater storage tank frame 1St  and 2nd
  • Steel pole tile 1st floor.
  • Tied steel frame elevator wall.
  • Laying steel base.
  • Tie steel frame base.
  • Tie steel pole 1st floor.
  • Setting main pipe system 1st   floor.
  • Pouring concrete base.
  • Install the plumbing system 1st floor.
  • Tied beam frame.
  • Pouring concrete beam.
  • Setting ground water system.Pouring concrete 1st floor.
NaN/6

Samui Water World building C
Koh Samui, Thailand

  • Tied steel frame elevator wall.
  • Pouring concrete poles.
  • Pouring concrete the groundwater storage tank.
  • Install the plumbing system 1st floor.
  • Pouring concrete post tensioned 1st floor.
  • Pile extraction.
  • Setting steel floor frame 1st floor
  • Steel pole tile 1st floor.
  • Pouring concrete 1st floor.
  • Pouring concrete pole 1st floor.
  • Setting up floor frame 2nd floor.
NaN/6

Samui Water World building D
Koh Samui, Thailand

  • Cut the foundation pile.
  • Tie steel frame base.
  • Steel pole tie 1st floor.
  • Pouring concrete base.
  • Pouring concrete pole 1st floor.
  • Setting up the scaffold for 2nd floor.
  • Tied steel beam pool bar.
  • Setting main water pipe system 1st floor.
  • Tied steel frame pool bar wall.
  • Install the plumbing system 1st floor.
  • Tile steel pole frame 1st floor.
NaN/6

Boutique
Pattaya, Thailand

Completed: 64 %
  • Plastering work on 6th floor 70% completed.
  • Exterior plastering work 85% completed.
  • Bricklaying on 7th floor 95% completed.
  • Tilling bathroom wall on 3rd-5th floor 95%completed.
  • Tilling bathroom wall on 6th floor 25%completed.
  • Tilling on 1st floor 60%completed.
  • Tilling  on 2nd-4th floor 80%completed.
  • Tilling on 5th floor 30%completed.
  • Ceiling work on 1st-4th floor 75% completed.
  • Ceiling work on 5th floor 20% completed.
  • Electric system work on 2nd-4th floor 92% completed.
  • Water drains work on 2nd-7th floor 85% completed.
     
NaN/11

Castle 1
Pattaya, Thailand

Completed: 100
  • Construction work 100% completed.
  • Architecture work 100% completed.
  • Sanitation systems work 100% completed.
  • Electric work 100% completed.
     
NaN/10

Castle 2
Pattaya, Thailand

Completed: 99 %
  • Bricklaying work on the underground floor 99% completed.
  • Plastering work on 1st-8th floor 98% completed.
  • Plastering wall work on rooftop floor 99% completed.
  • Plastering underground wall 99% completed.
  • Wash basin counter work 85% completed.
  • Tilling work on 1st-8th floor 99% completed.
  • Tilling work on rooftop floor 99% completed.
  • Install skirting boards 95% completed.
  • Install wood door 30% completed.
  • Outdoor painting work 40% completed.
  • Interior wall painting work 80% completed.
  • Ceiling work 70% completed.
  • Installing UPCV window on 2nd-7th floor 80% completed.
  • Elevator work 80% completed.
  • Electric system work 1st-8th floor 99% completed.
  • Water system work 97% completed.
NaN/10

Castle Hotel
Pattaya, Thailand

  • Electric system on 2nd floor.
  • Painting ceiling work on 2nd floor.
  • Wall work on 1st floor.
  • Roof top work.
  • Installing Air condition on 2nd floor.
NaN/5

Club 3
Pattaya, Thailand

Completed: 100
  • Almost completed (Just wait for cleaning).
  • Open on August 2019
NaN/9

Club 4
Pattaya, Thailand

Completed: 91 %
  • Ceiling work on 1st floor 40% completed.
  • Ceiling work on 2nd-7th floor 99% completed.
  • Swimming pool electrical system work 98% completed.
  • Exterior painting work 95% completed.
  • Painting in the room on 2nd-7th 99% completed.
  • Water drains work on 2nd-7th floor 99% completed.
NaN/11

Club 5
Pattaya, Thailand

Completed: 5 %
  • Adjust the soil 70% completed.
  • Pouring foundation concrete 55% completed.
NaN/6

Palace Hotel
Pattaya, Thailand

Completed: 13 %
  • Retaining wall 100% completed.
  • Sheeting support pole on 1st floor 60% completed.
  • Setting elevator plan underground floor 50% completed.
NaN/6

Bangtao Water World B
Phuket, Thailand

  • The entrance of the road work from public road to the construction site completed.
  • Digging foundation work for building B.
  • Building the retaining wall block.
  • Making a foundation work of retaining wall.
  • Steel building wire work for the base of retaining wall keep going.
  • The piling work of building C completed.
NaN/8